Leith Programme – Update

(Adapted from an email from Leith Links CC)

Progress update

All work is currently running on schedule to the programme timescale

Section 6a West (Balfour Street southwards):

  • All kerbs re-laid south of Balfour Street
  • 75% of existing slabs removed
  • 25% of new slabs re-laid

Section 6a East (Jameson Place southwards)

  • 50% of existing slabs removed
  • 15% new slabs re-laid
  • Trial hole to relocate lighting column completed

Section 8a West (Jane Street southwards)

  • 40% of existing slabs removed
  • New gully connection complete
  • Installation of kerbs 50% complete
  • 20% of new slabs re-laid

Section 8a East (South of Manderston Street)

  • 50% of existing slabs removed
  • Installation of kerbs 75% complete
  • 15% of new slabs re-laid

Other sections:  

  • Snagging works to sections 5 and 7 on-going

Looking ahead for next week:

  • Continue with footpath works in all sections
  • Relocate lighting columns in sections 6 and 8
  • Gully installation at Stead’s Place

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s